Schumannstraße between Meißner Straße and Pestalozzistraße

© Stadtverwaltung Radebeul
Vor der Baumaßnahme

© Stadtverwaltung Radebeul
Nach der Baumaßnahme
Reason and objective |
Fundamental road construction including pavements in connection with the sewage-side development, the replacement of the drinking water pipes |
Planning |
ACI Ingenieurgesellschaft from Dresden/Radebeul |
Construction period |
September 2019 to July 2020 |
Construction work |
Heinrich Lauber GmbH & Co. KG, Coswig |
Costs/ financing |
approx. 110,000 € |